By Dave Shewring, Head of Laboratory Services
A laboratory move affects much more than the equipment being transported. It can interrupt research, expose sensitive samples to risk, trigger complex equipment recommissioning and place pressure on research teams who still need to deliver results. The best relocations are therefore designed around scientific continuity, risk mitigation and not just a logistics plan.
We asked Dave Shewring, Divisional Lead – Life Sciences at Harrow Green, to explain where organisations should focus before committing to a relocation programme.
When should a laboratory involve a specialist relocation partner?
As soon as a relocation becomes a credible possibility, ideally while the business case, building layout and overall programme are still being shaped. Early advice allows laboratory-specific requirements to influence the design rather than being discovered after critical decisions have been made.
A relatively straightforward departmental move may be planned quickly. A large, multi-phase scientific relocation can require many months, even years, of preparation, particularly when OEMs, hazardous materials, temperature-controlled samples and new-building interfaces are involved. There is no one-size-fits-all lead time.
What information should be established before requesting a detailed price?
Start with the operating requirements: what work must continue, what can pause, which assets are critical to the research programme, and when each laboratory can realistically become unavailable with planned downtime.
Then build an initial equipment and materials inventory, identify specialist instruments, define the origin and destination, and record known programme constraints. An early budget may be possible with assumptions, but a reliable move plan and commercial baseline depend on validating those assumptions.
Why is the equipment asset list so important?
An asset list is not simply a count of instruments. For each relevant item, the team may need to know its exact location, make and model, size and weight, packaging or access needs, service dependencies, cleaning or decontamination requirements, relocation responsibility and the activity required to return it to use.
It also needs active ownership. Asset registers evolve as laboratories change, research programmes advance and instruments are added, retired or relocated internally. If the list is incomplete or frozen too early, the programme can be built around a version of the laboratory that no longer exists.
How do you decide whether an OEM or the relocation team should move an instrument?
This should be agreed for each relevant asset, not assumed by either side. Some equipment can be prepared and transported by a suitably competent specialist relocations team; other instruments require an OEM or approved third party to perform particular steps because of warranty, technical, calibration or validation requirements.
The crucial point is to document who will decommission, disconnect, package, handle, transport, reinstall, commission and, where applicable, qualify each asset. The same plan should capture lead times, booking dependencies and what happens if an OEM date changes. Ambiguity here often produces cost, delay and risk.
How can organisations protect scientific work and minimise downtime?
Work backwards from the moment each laboratory or instrument needs to be usable again. Different research teams will have different acceptable downtime windows, critical materials and dependencies. A phased move can protect essential capability, but only if the temporary and receiving arrangements support it.
Samples, reagents and temperature-sensitive materials need their own risk-based transfer plan, including appropriate packaging, temperature control, monitoring, chain of custody and credible contingency arrangements. Restart criteria should be agreed in advance: “delivered” does not necessarily mean “ready for science”.
Why can a new laboratory be finished but still not ready to receive equipment?
Construction completion and operational readiness are different milestones. Before delivery, the team must check practical access routes, lifts and loading areas, equipment footprints and floor-loading requirements, and any relevant electrical, gas, water, ventilation, network or environmental services.
There must also be a clear route for installation, OEM attendance, testing and handover. It is far better to expose a missing utility, an unsuitable route or an unresolved installation dependency during a readiness review than to discover it after a specialist instrument arrives.
What are the mistakes you most often advise clients to avoid?
Treating relocation as a final-stage logistical task; relying on an unverified asset list; involving OEMs too late; overlooking dangerous goods and sample-handling requirements; underestimating the time scientists must spend making decisions; and using a construction handover date as if it were the same as a fully operational start date.
Another common weakness is failing to agree who is authorised to make scope and programme decisions. Laboratory relocations involve researchers, facilities, IT, health and safety, building contractors, equipment specialists and the relocation team. Without named decision-makers and disciplined change control, even a technically sound plan can lose momentum.
What does a well-planned laboratory relocation look like?
There is a validated and actively maintained asset register, an integrated move and recommissioning programme, accountable owners for every specialist interface and an agreed definition of when each laboratory is operational again.
Risks and contingencies are visible, not buried in assumptions. The project team knows which decisions are due, which equipment is on the critical path and what must happen if a date or dependency changes. Above all, the programme protects the scientific work that the new facilities were built to support.
At Harrow Green, our laboratory relocation teams support organisations from early scoping and asset surveys through specialist project management, laboratory readiness, equipment logistics and coordination with OEMs and other specialist providers. If a laboratory move is being considered, an early conversation can help clarify the scope and the decisions that matter most.